Date of Notice |
29 July 2024 |
Period of Work |
29 July and 2 August 2024 |
Time |
0800hrs to 1200hrs |
Location |
29 July 2024 Marina Reservoir, Kallang Basin
2 August 2024 New Merlion Park, Esplanade Park, Marina Bay, Queen Elizabeth Wall |
Craft |
RC 489 |
Contact Person |
Delta Marine Consultants Singapore Pte Ltd Prashant Hingwe - 82498040
|
29 July 2024
1. Delta Marine Consultants Singapore Pte Ltd is appointed consultant by Building and Construction Authority to conduct inspection of seawall (vertical wall) and revetment at Kallang Basin on 29 July 2024.
2. RC 489 work boat would be deployed to allow inspectors/engineers access to the vertical wall and revetment for visual inspection.
3. RC 489 work boat will be mobilized from Launching Platform at Kallang Basin (near public toilet B along republic avenue).
4. For more information. please refer to the schedule of works below.
Date |
Inspection Location |
Working Hours |
29 July 2024 |
Vertical wall and revetment at Kallang Basin |
0800hrs to 1200hrs |
5. All vessels are advised to keep clear of the inspection work areas and slow down when in the vicinity.
2 August 2024
1. They are also appointed to conduct inspection of pile-deck and seawall (vertical wall) at New Merlion Park, seawall (vertical wall) at Esplanade Park, seawall (vertical wall) at Marina Bay and revetment at Queen Elizabeth Walk on 2 August 2024.
2. RC 489 work boat would be deployed to allow inspectors/engineers access to the pile deck structure, seawall and revetment for visual inspection.
3. RC 489 work boat will be mobilized from Raffles Place Jetty.
4. For more information. please refer to the schedule of works below.
Date |
Inspection Location |
Working Hours |
2 Aug 2024 |
1. Pile-deck and Seawall (vertical wall) at New Merlion Park 2. Seawall (vertical wall) at Esplanade Park 3. Seawall (vertical wall) at Marina Bay 4. Revetment at Queen Elizabeth Walk |
0800hrs to 1200hrs |
5. All vessels are advised to keep clear of the inspection work areas and slow down when in the vicinity.